New PMP Question & Answers with explanation
You are the Project Manager for JT's Lumber Yard. You are trying to forecast estimates for the final phase of the project you are currently working on. Based on the performance of the project to date, which formula can be used to estimate the total value of the project when completed, assuming similar variances will not occur?
Select one
You are a project manager who is in charge of an important project for your company. The project is 40 percent complete after three months and has cost $350,000. The budget for the project is $950,000 and is scheduled to last eight months. How is the project performing?
Select one
Which of the following estimating techniques will cost less but is also typically less accurate?
Select one
The cost of running a project management office is an example of what type of cost?
Select one
Which of the following methods of forecasting EAC and ETC is the most accurate?
Select one