New PMP Question & Answers with explanation

Identification of new risks, reassessment of old risks, and closing of outdated risks are part of the Monitor Risks process. How often should project risk reassessment be scheduled?
Select one
A small project with a limited budget is trying to curtail costs. Which of the following processes may be eliminated in such a project?
Select one
You are the project manager of a project and are about to conduct a risk identification exercise in a few days’ time. You want to remind the participants in the exercise beforehand of the various sources from which risk may arise in the project. What could you use to help you do this?
Select one
A number of identified risks occurred early in a project. As a result, most of the project objectives ended up in jeopardy. The project manager decided to present a case to management that the project be closed down. This is an example of:
Select one
Prompt lists are usually developed based on historical information and knowledge accumulated from previous similar projects. Which of the following statements about risk prompt lists is wrong?
Select one