New PMP Question & Answers with explanation
You are just about to present your project’s status to your company’s executive team. Just as you are leaving your desk for the meeting, one of your resources hands you an updated report on the progress of a critical deliverable. As you are walking to the conference room, you review the report and notice there is an error in it. What do you do?
Select one
A new project manager has just taken over a project that is 50 percent complete. As part of the hand-over process, the outgoing project manager provided the new project manager with a list of stakeholders that needed to be managed. The list had been compiled at the start of the project. Which of the following is true about stakeholders?
Select one
Kelly is part of a project management office (PMO). Her office is responsible for the centralized and coordinated management of 18 projects. Each project has its own project manager. Which of the following will not typically be a responsibility of her PMO?
Select one
A project manager used the services of a trained moderator during the Collect Requirements process. Which of the following is likely to have required the services of a trained moderator?
Select one
A project manager uses the precedence diagramming method (PDM) for constructing a project schedule network and creates a network diagram for the purpose. He decides to use the most common type of precedence relationship for all activities. Which of the following relationships would he use?