New PMP Question & Answers with explanation
Project costs are estimated for all project activities and are aggregated to establish a cost baseline. Which of the following statements about the cost baseline is not true?
Select one
Rodney is in the process of preparing the project performance report for the team meeting. He is expecting many questions from his stakeholders on the budget and schedule. He calculates the following values: Budget at Completion (BAC) = $22,000, Earned Value (EV) = $13,000, Planned Value (PV) = $14,000, Actual cost (AC) = $15,000. What is the Estimate at Completion (EAC) for the project, if the work is performed at the budgeted rate?
Select one
Which of the following statements about the planned value, the earned value, the schedule variance, and the cost variance of a project is false?
Select one
During the course of the project, the project management team developed a forecast for the estimate at completion (EAC) based on the project performance. Which of the following statements about EAC is correct?
Select one
Variance Analysis is an important tool used in the Control Costs process. Which of the following statements regarding variances is correct?
Select one