New PMP Question & Answers with explanation
You have recently taken over a troubled automobile project, which has gone out of control. The project team missed many deadlines, and stakeholders were displeased with the project’s progress. As an experienced project manager, your first priority is to align the schedule with the project plan. You would like to use what-if scenario analysis to see how various factors affected the project schedule so you can develop a plan to reduce the impact of adverse conditions on the project schedule in the future. What would be your next course of action be, once you determine the factors that created schedule overruns?
Select one
A project manager has just started planning his project. If he has only limited information about the project, he should use the following technique to estimate the duration for each activity using historical data from a similar project:
Select one
You are working as a project manager for a high-yield crop development project. Data from the weather agency shows an unfavorable weather pattern for the next few months. As a senior project manager, you want to assess the schedule’s feasibility under adverse conditions and provide some insights to your team. That way, your team can prepare some reserves and plan risk responses if unfavorable conditions exist during execution. Which of the following techniques should you use to simulate risks and other sources of uncertainty to calculate possible schedule outcomes?
Select one
You are managing a heavy equipment manufacturing project that involves many mechanical, electrical, and IT staff. Your team prepared a schedule network diagram using duration estimates with dependencies and constraints. Your team also calculated the critical path for the project using late and early values. Today, your project office has indicated to you that some of the resources you had planned for the project will be unavailable. To deal with this, you explore the possibility of modifying the schedule to account for limited resources. What is your best possible step in such a situation?
Select one
All the following are tools of the Control Schedule process except:
Select one