New PMP Question & Answers with explanation

Which of the following are all items included in the cost management plan?
Select one
Your company is undergoing a change in ownership and the new owners are looking at the total cost of a new product. Which of the following would best provide that information
Select one
You are tracking your project using earned value management (evm) and find you are behind schedule but under budget. Your variances show schedule variance (SV) = -us $50 million, cost variance (CV) = $100 million, and your actual costs are us $500 million. What are the cpi, pv and spi?
Select one
A project manager has just been notified of a cost increase by a seller. He looks at the contract and determines that the seller has the right to pass along this cost increase. The project manager should fist determine if
Select one
What does estimate at completion (EAC) mean
Select one