New PMP Question & Answers with explanation

You are managing a hotel construction project, and you have asked your project team to calculate the current earned value metrics to determine the project performance. Your team reports back that the project's to-complete performance index (TCPI) is 0.9 based on the budget at completion (BAC). Which of the following is true regarding your project's current situation as reflected by this TCPI value?
Select one

While looking at the project cost baseline graph shown below, a project manager sees that the stair-step line’s last point is higher than the estimate at completion (EAC). What does this relationship mean for the project?


Select one

For the project with Earned Value (EV) = $350, Actual Cost (AC) = $300 and Planned Value (PV) = $400. The original project budget is $1,000. Assuming the remaining work will be impacted by the current cost performance and current schedule performance, what is the Estimate At Completion (EAC) of the project?

Select one

For the project with Earned Value (EV) = $300,  Actual Cost (AC) = $250 and Planned Value (PV) = $300. The original project budget is $1000. Assuming the project will continue to spend money at the same rate, what is the Estimate At Completion (EAC) of the project?

Select one

For a project with Earned Value (EV) = $300, Actual Cost (AC) = $350 and Planned Value (PV) = $400. The overall project budget is $1,000. Assume that you will continue to spend at the same rate as you are currently spending. What is the Variance At Completion (VAC)?

Select one