New PMP Question & Answers with explanation

A project manager notifies the project sponsor that the mitigation strategy for a major risk did not work. The sponsor states that the same risk response was implemented a few months ago on a similar project with the same result. How might this situation have been avoided?
Select one
A project manager has just learned that the customer is not showing up to requirements meetings saying they have other more important tasks. Since this behavior has already been identified as a risk earlier in the project, the project manager escalates the issue to the stakeholder who is the risk owner responsible for communicating with the customer in such situations. The stakeholder is shocked to find out she is the assigned risk owner. What most likely went wrong?
Select one
With a parking garage construction project underway, you are currently creating the risk management plan. In support of this process, you need to determine the acceptable level of overall project risk exposure. What should you do first?
Select one
A project team performs monthly risk audits for a project in which a large number of identified risks have been realized. So far, the risk responses have been appropriate, and reserves are sufficient. An executive for the requesting organization chides the project manager for doing risk audits improperly, stating that like all audits, outside independent resources need to perform risk audits. How should the project manager respond?
Select one
Your risk report shows that project risk exposure overall has grown close to a negative threshold. Before the next regular meeting, you ask risk owners to present any risks and opportunities that may affect short-term activities. In the meeting, it becomes clear that risk owners from less engaged departments did not implement some of the previously approved responses. What should you do now to reduce risk exposure?
Select one