You are leading a project to design a high-efficiency solar cell. The materials that you are acquiring for this project include copper, silver, and silicon among others, and you have also ordered custom built manufacturing equipment. Additionally, you have secured permission from the landlord to install a solar array on the roof of the corporate office for testing, and reserved a conference room for daily stand-up meetings. What is the result of your efforts?
Select one
You are leading a project team with a technology upgrade project within a project-oriented organizational structure. You were recently informed that one of your project team members falsified required certifications on their resume', and you have verified the information as accurate. You want to terminate the team member's employment. What should you do first?
Select one
A project to construct a new subway line is underway, and the tunnel boring machine has slowed due to unexpected changes in rock composition. It has been decided to implement the planned risk response by increasing the speed of the machine to 100% of rated capacity. The team believes that the additional strain on the machine will not cause more downtime for its maintenance thus negating the benefit of faster boring. What should the project manager do first?
Select one
A project is underway to construct a 50 story office building. With construction nearly complete, a government inspector has issued a stop order because one of the cranes failed inspection. The schedule reserves are inadequate to cover the resulting delay from the unavailability of the key resource. What should the project manager do next?
Select one
As a project manager, you are leading a software development project where the developers are colocated within rented office space. Writing the code is taking longer than anticipated, and you have contacted the office facility to ensure the office will be available for another week. Unfortunately, the office is already booked, so you need to find another solution. After capturing the problem in the project documents, what should you do next?
Select one