New PMP Question & Answers with explanation
Which of the following does a project manager use to build trust with stakeholders and overcome resistance to change?
Select one
Alyssa is a project manager tasked with managing an infrastructure project that will consolidate five data centers into one. She has used a waterfall approach to carry out initial planning activities and is executing the work using an Agile-based approach. This hybrid approach is new to her and the team. After completing their second iteration, Alyssa gets the team together to brainstorm how they can continue to improve the process. One team member with experience using Agile approaches recommends getting together at the conclusion of each iteration to talk about what went well, what could be improved, and what they will commit to change during the next iteration. What is the team member recommending?
Select one
You are a senior project manager working at a manufacturing plant that produces components used by the aviation industry. You are using a predictive life-cycle approach and are in the process of implementing approved changes. What key information will you need to successfully complete the associated activities?
Select one
Making small, incremental improvements within a product or process is known as:
Select one
Nicolas is the sponsor of a project that will replace all equipment that has already surpassed its end of lifetime span. He decides to assign this project to Carina, his topperforming project manager. Carina’s first task will be to write the project charter. Who will be responsible for signing the project charter document, thereby approving the project?
Select one