New PMP Question & Answers with explanation
Your project has a high degree of uncertainty about the project requirements. You decide to use an agile approach to manage the project in order to achieve which of the following?
Select one
You are using criticality analysis to determine risk impact. You have calculated an index for each risk and realize the more activities the risk impacts, the higher the index. The index is used as an input to a simulation. Which risk does criticality analysis assess?
Select one
You are performing the Perform Qualitative Risk Analysis process and want to display proximity and connectivity and their impacts on the project. Which of the following methods will you use?
Select one
You are using the representations of uncertainty technique of the Perform Quantitative Risk Analysis process. All of the following statements are true regarding this technique except for which one?
Select one
Which of the following describe the purpose for the risk management plan?
Select two