New PMP Question & Answers with explanation
You work for a furniture manufacturer. Your project is going to design and produce a new office chair. The chair will have the ability to function as a regular chair and also the ability to move its occupant into an upright, kneeling position. The design team is trying to determine the combination of comfort and ease of transformation to the new position that will give the chair the best characteristics while keeping the costs reasonable. Several different combinations have been tested. This is an example of which of the following techniques?
Select one
The quality management plan documents how the project team will implement the quality policy. It should address at least which of the following?
Select three
Which of the following describes the cost of quality associated with scrapping, rework, and downtime?
Select one
Which of the following are benefits of meeting quality requirements?
Select four
The theory that 85 percent of the cost of quality is a management problem is attributed to ___________________.
Select one