New PMP Question & Answers with explanation

You know that BAC = 2500, PV = 1250, AC = 1275, EV = 1150, and that you are experiencing typical cost variances. What is ETC?
Select one
You know that BAC = 500, PV = 325, AC = 275, CPI = 0.9, and EV = 250, and you are using actual costs to date and assuming ETC uses the budgeted rate. What is Variance at Completion?
Select one
You expect future project performance to be consistent with the project performance experienced to date for this work component. If BAC = 800, ETC = 275, PV = 300, AC = 200, EV = 250, and CPI = 1.25, what is the EAC?
Select one
You know that EAC = 375, PV = 300, AC = 200, and EV = 250. You expect the work of the project to continue as planned. What is the ETC?
Select one
You have accepted project performance to date and assume future work (ETC) will be performed at the budgeted rate. If BAC = 800, ETC = 275, PV = 300, AC = 200, EV = 250, and CPI = 1.25, what is the EAC?
Select one