You are reviewing the expense report form one of your team members when you notice a payment he made in another country. You think the payment is bribe. What is your first course of action
Select one
Which of the following is an example of a parametric estimate?
Select one
You are a project manager for a small construction project. Your project was budgeted for u.s. $72,000 over a six week period. As of today, you've spent u.s. $22,000 of your budget to complete work that you originality expected would cost u.s. $24,000. According to your schedule, you should have spent u.s. $30,000 by this point. Based on these circumstances, your project could be best described as:
Select one
A definitive estimate is in a range from
Select one
Which of the following are all items included in the cost management plan?
Select one