New PMP Question & Answers with explanation

When possible, the detailed project schedule _________ throughout the project to adjust for knowledge gained, increased understanding of the risk, and value-added activities.
Select one
Calculation of late finish dates and late start dates for the uncompleted portion of the project is called ____________.
Select one
Your company is way behind schedule in the deployment of a government-mandated change to a health care processing system that must be in production by the end of the year. To meet the due date, you and your team have met and decided to hire an additional 50 programmers to work with the existing staff. This is an example of what?
Select one
As the project manager of a project, you had estimated certain activity durations before acquiring all project team members. On acquisition, you find that their actual competency levels are much lower than what you anticipated. In such a case, you will:
Select one
You have a schedule activity that can be delayed without delaying the early start date of any subsequent activities. This is an example of:
Select one