New PMP Question & Answers with explanation

The list of identified risks is found in the risk register. However, the overall high-level project risks is first listed in the:
Select one
You are a project manager creating the final project report. Which information would you NOT include in this report?
Select one
You are the project manager for GeoThermal Systems. Which of the following must be done FIRST before proceeding with a new project?
Select one
Julia is managing a software development project. Recently, an unexpected event delayed the project by 15 days. Julia has called a team meeting to identify measures to take to bring the project back on schedule. A measure that is taken to bring future results back in line with the project plan is best described as?
Select one
The selection of lifecycle for the project, the processes to be applied to each phase, and the results of the tailoring by the project management team are usually found in the:
Select one