New PMP Question & Answers with explanation

You are two days late on reporting the status for a project you are managing. The status report indicates that the project is lagging behind schedule. During the current week, you are confident of making up some of the lost time. How should you report project status?
Select one
The Code of Ethics and Professional Conduct has as its foundation four values identified by practitioners from the global project management community. They are:
Select one
Which of the following are more important inputs to the Manage Stakeholder Engagement process in relation to the others?
Select one
Which of the following allows a project management team to communicate all approved and rejected changes to the stakeholders consistently?
Select one
A project manager prepared a composite resource calendar. Which of the following is unlikely to be part of the resource calendar?
Select one