New PMP Question & Answers with explanation

As part of a strategy to handle negative risk, a project manager decided to adopt less complex processes, conduct more tests, and choose a more stable supplier. What strategy would this be classified as?
Select one
At the beginning of the project, a project manager realized the technical expertise of the team was limited, a risk to the project. Midway through the project, the project manager decided that this was no longer a risk and considered it outdated. As part of which process would he do the risk reassessment?
Select one
If a project has a 60 percent chance of a $100,000 profit and a 40 percent chance of a $100,000 loss, the expected monetary value of the project is:
Select one
During which stage of risk planning are risks prioritized based on their relative probability and impact?
Select one
Which of the following is true about risks?
Select one