New PMP Question & Answers with explanation
A manager notices that a project manager is holding a meeting with some of the team and some stakeholders to discuss the quality of the project. The project schedule has been compressed and the cpi is 1.1. They have worked hard on the project, the team has been rewarded according to the reward system the project manager put in place and there is a strong sense of team. The manager suggests that the project manager does not have enough time to hold meetings about quality when the schedule is so compressed. Which of the following best describes why the manager is wrong?
Select one
A project manager has just taken over the project from another project manager during the executing process group. The previous project manager created a project budget. Determined communications requirements and went on to complete work packages. What should the new project manager do next?
Select one
A control chart helps the project manager:
Select one
All of the following are inputs to the quality process except?
Select one
A control chart indicates the last 12 weights produced were outside the upper control limit. What should the project manager do?
Select one