The difference between project deliverables and project requirements is best described in which of the following options?
Select one
A project sponsor asks the project manager to observe nonverbal feedback in the upcoming status meeting and adjust his presentation based on these observations. Which process is associated with these activities?
Select one
The project team recently participated in a working session to examine and document the effectiveness of risk responses in dealing with overall project risk. What project management process are they performing?
Select one
The project manager has just determined that three functional managers with a high interest in the project hold a particularly high degree of influence in the allocation of enterprise resources. In what activity is the project manager involved?
Select one
Match the PMO type with its corresponding description.
Matching
PMO Type Description
Supportive
Serves in a management role. Assigns project managers to projects and directly manages projects
Controlling
Serves in a consultative role. Provides templates, best practices, training, and lessons learned from other projects
Directive
Serves in a supportive and compliance role. Provides project management and governance frameworks that are followed by PMs