New PMP Question & Answers with explanation
A project manager is performing quantitative risk analysis. What output is likely to be produced?
Select one
You are the project manager for Kitchens Plus Inc. The latest project involves the development of an automatic dicer with unique industry features and has a project budget of $95,000. Based on the latest data, the project has a planned value of $70,200, an earned value of $59,000, and an actual cost of $65,500. How is the project currently performing according to the schedule and budget?
Select one
All of the following are true regarding EMV analysis except for which one?
Select one
During a status meeting, the project manager informs the team that the project has spent a total of $7,500 to date and that the earned value is $5,000. How is the project currently performing?
Select one
Carina is a principal project manager of You’ve Got Dogs, a specialty company that creates custom dog apparel and toys. She has just obtained approval of the project management plan and is about to publish it to the project team. At this point in the project life cycle, costs are likely to be which of the following?
Select one