New PMP Question & Answers with explanation

The output of the Monitor and Control Project Work process can take many forms, including issues or action item logs, status reports, project documents, dashboards, and more. Which output does this refer to?
Select one
Which of the following best describes the value of respect that project management practitioners should follow?
Select one
If Activity A has an early start of 10, an early finish of 16, and a late start of 12, what is the total float of the activity?
Select one
All of the following statements about the arrow diagramming method (ADM) are true except for which one?
Select one
Maslow’s Hierarchy of Needs is a motivational theory that notes that humans have five basic needs arranged in a hierarchical order. What is the highest set of needs of the five within the hierarchy?
Select one