New PMP Question & Answers with explanation
The lowest level of the work WBS is the:
Select one
To expedite the scheduling process, a project manager alters an existing schedule management plan from a previous project for use on the current project. In this case, the schedule management plan represents:
Select one
Which contract type poses a higher risk for the buyer?
Select one
Al is a lead testing manager, and Veronica is a development manager; both work for Power Cloud Stock Trading Online. They are requesting a meeting with the project manager because every milestone that has been set for the project seems to experience a conflict. The top three reasons for conflict are:
Select one
Crystal is a family of methodologies intended to support a wide range of projects, depending on project size and criticality. Match the Crystal Method used when basing the selection solely on the range of stakeholders involved.
Matching
Crystal Methods | ||
Crystal Method Name | Number of Stakeholders Involved | |
Crystal Clear
|
20 to 40 people
|
|
Crystal Yellow
|
5 to 100 people
|
|
Crystal Orange
|
6 to 20 people
|
|
Crystal Red
|
1 to 4 people
|