You are working on a project that will upgrade the phone system in your customer service center. You have considered using analogous estimating, parametric estimating, bottom-up estimating, and three-point estimating to determine activity costs. Which process does this describe?
Select one
All of the following are a type of project ending except for which one?
Select one
You are a project manager working on a software development project. You've developed the risk management plan, identified risks, and determined risk responses for the risks. A risk event occurs, and you implement the response. Then, another risk event occurs as a result of the response you implemented. What type of risk is this?