Your Scrum team's velocity rate is 24 story points per iteration. There are 165 total story points. Which of the following statements are true regarding this question?
Select two
You are the project manager for Rivera Gourmet Adventure Vacations. Rivera combines the wonderful tastes of great gourmet food with outdoor adventure activities. Your project involves installing a new human resources software system. Your stakeholders understand this is a large undertaking and that you might experience some schedule slippage. Jason, the database analyst working on this project, is overallocated. He is critical to the success of the project, and you don't want to burn him out by overscheduling him. Which of the following actions should you take?
Select one
You are the project manager working on a research project for a new drug treatment. Your preliminary project schedule runs past the due date for a federal grant application. The manager of the R&D department has agreed to release two resources to work on your project to meet the federal grant application date. This is an example of ______________.
Select one
This contains all the supporting detail regarding activity estimates and includes assumptions, the methods used to derive the estimates, constraints, resources used to develop the estimates, confidence levels, and risks.
Select one
If you know the expected value is 500 and the standard deviation is 12, you can say with approximately a 95 percent confidence rating which of the following?
Select one