New PMP Question & Answers with explanation

You are using a defined set of risk categories to determine both individual risks and overall project risks. You will also use PESTLE, a strategic analysis tool to assist in determining overall project risk. You are also using the lowest level of the RBS to help in constructing which of the following in order to identify risks?
Select one
Your project team has identified several potential risks on your current project that could have a significant impact if they occurred. The team examined the impact of the risks by keeping all the uncertain elements at their baseline values. Which of the following will the team use to display this information?
Select one
You work for a large manufacturing plant. You are working on a new project to release an overseas product line. This is the company's first experience in the overseas market, and it wants to make a big splash with the introduction of this product. The stakeholders are a bit nervous about the project and historically proceed cautiously and take a considerable amount of time to examine information before making a final decision. The project entails producing your product in a concentrated formula and packaging it in smaller containers than the U.S. product uses. A new machine is needed to mix the ingredients into a concentrated formula. After speaking with one of your stakeholders, you discover that this will be the first machine your organization has purchased from your new supplier. Which of the following statements is true given the information in this question?
Select one
Risk attitude is an enterprise environmental factor that you should evaluate when performing the Plan Risk Management process. Risk attitude consists of which of the following elements?
Select two
Your hardware vendor left you a voicemail saying that a snowstorm in the Midwest will prevent your equipment from arriving on time. You identified a risk response strategy for this risk and have arranged for a local company to lease you the needed equipment until yours arrives. This is an example of which risk response strategy?
Select one