New PMP Question & Answers with explanation
Match the following agile measurements with their definitions.
Matching
Agile measurements and definitions | ||
Agile measurements |
Agile measurements and definitions | Agile measurements | Definitions
|
Definitions |
Capacity measures
|
A checklist of elements needed to ensure the deliverable is ready for the customer to use
|
|
Definition of done
|
The time it takes for a task to go from request to completion
|
|
Lead time
|
Describes the specifics of the tasks planned for the iteration before the team begins work
|
|
Empirical measure
|
The time it takes to complete work on a task from the time work starts
|
|
Cycle time
|
The time a task waits before work starts
|
|
Response time
|
A type of in-the-moment measure
|
|
Definition of ready
|
Typically expressed as deliverables, functionality, or features
|
This tool and technique of the Close Project or Phase process looks at project variables and how they contributed to project outcomes. This is for the purpose of improving performance on future projects.
Select one
You are a contract project manager working with the State of Bliss. Your latest project involves rewriting the Department of Revenue's income tax system. As project manager, you have taken all the appropriate actions regarding confidentiality of data. One of the key stakeholders is a huge movie buff, and she has the power to promote you into a better position at the conclusion of this project. She's reviewing some report data that just happens to include confidential information regarding one of her favorite movie superstars. What is the most appropriate response?
Select one
You know that BAC = 2500, PV = 1250, AC = 1275, EV = 1150, and that you are experiencing typical cost variances. What is ETC?
Select one
You know that BAC = 500, PV = 325, AC = 275, CPI = 0.9, and EV = 250, and you are using actual costs to date and assuming ETC uses the budgeted rate. What is Variance at Completion?
Select one