New PMP Question & Answers with explanation
Progressive elaboration is least applicable to which of the following processes?
Select one
The project management team expects that during the course of the project there could be delays in component delivery due to strikes, changes to the permitting processes, or extensions of specific engineering durations. What analysis could be helpful in preparing contingency and response plans to mitigate these issues?
Select one
Ron is a project manager handling an alternate water-supply project. During a project performance review, he notices the following: (i) Activity A, on the critical path, is delayed by four days. (ii) Activity B, not on the critical path, is delayed by nine days. (iii) Activity C, on the critical path, is delayed by two days. (iv) Activity D, not on the critical path, is delayed by five days. In what sequence should Ron prioritize his efforts in addressing these delays?
Select one
Activity attributes extend the description of the activity by identifying various components associated with the activity. Typically, how many attributes are associated with each activity?
Select one
While sequencing activities for a project, the project management team applied certain discretionary dependencies. This was based on their knowledge of best practices within the project application area. What is the potential risk involved in using such dependencies?
Select one