New PMP Question & Answers with explanation
Late in the project cycle, it was discovered that some of the project’s human resources should have trained in a specific methodology. Where should these training strategies have first been documented?
Select one
A project manager would like to resolve conflicts by a give-and-take attitude rather than by a one-sided approach. Which of these approaches is he likely to use?
Select one
Public recognition of superior performance creates positive reinforcement for the team members. When is the best time for a project manager to recognize team members' performance?
Select one
The morale of the team members of a project is very low. The team members feel they were not given opportunities to participate in the organizational team development activities due to over-allocation to project tasks, and so, they missed opportunities to develop. Which of the following is the most likely cause of this situation?
Select one
All team members have not yet been hired for a project. However, the project manager went ahead with estimating activity durations, budgeting, and other activities. What could likely happen to the activity durations?
Select one