Bill and Jake are two team members in a project. They do not get along well and are constantly involved in verbal conflicts. The project manager understands the characteristics of conflict and the conflict management process and tries to resolve the situation. Which of the following is not a correct statement?
Select one
While preparing a resource management plan, a project manager designated one of the senior programmers on the team to make decisions on whether the quality of deliverables met the project's documented standards. Which of the following aspects of a resource management plan does this address?
Select one
A critical resource is on another project team. It is essential that you get his time for your project. You have contacted the resource’s team manager several times but have received a poor response. What should you consider doing next?
Select one
Teams go through various stages of development. According to the Tuckman ladder of development, the stage during which the least amount of work gets done is usually the:
Select one
Late in the project cycle, it was discovered that some of the project’s human resources should have trained in a specific methodology. Where should these training strategies have first been documented?