New PMP Question & Answers with explanation
During the conceptual phase of a pipeline project, the project engineer estimates the following. The cost of the materials is most likely us $100,000, optimistically u $90,000, and pessimistically us $120,000. The cost for labor is most likely us $80,000, optimistically us $70,000, and pessimistically us $100,000. The cost for equipment is most likely us $60,000, optimistically us $50,000, and pessimistically us $70,000. The cost for construction management fees is most likely us $30,000, optimistically us $20,000, and pessimistically us $40,000. What is the probability of the project coming in under us $270,000?
Select one
Value analysis is performed to get:
Select one
Advantage of bottom-up estimates
Select one
During which project management process group are budget forecasts created?
Select one
In which part of the cost management process is earned value (EV) used
Select one