New PMP Question & Answers with explanation
In which part of the cost management process is earned value (EV) used
Select one
You are reviewing the expense report form one of your team members when you notice a payment he made in another country. You think the payment is bribe. What is your first course of action
Select one
Which of the following is an example of a parametric estimate?
Select one
You are a project manager for a small construction project. Your project was budgeted for u.s. $72,000 over a six week period. As of today, you've spent u.s. $22,000 of your budget to complete work that you originality expected would cost u.s. $24,000. According to your schedule, you should have spent u.s. $30,000 by this point. Based on these circumstances, your project could be best described as:
Select one
A definitive estimate is in a range from
Select one