Status review meetings are an important tool for informing stakeholders (and others) of the status of the project. All of the following are true regarding status review meetings except for which one?
Select one
All of the following processes belong to the Project Integration Management Knowledge Area except for which one?
Select one
A project manager facilitates a meeting to provide updated information regarding the progress of the project. What type of meeting is this?
Select one
A project manager has structured his project in a way that will allow for the planning of the project to occur during the early phases of the life cycle, with minimal changes thereafter. This approach is associated with which development life cycle?
Select one
Match the project life cycle with its respective description.
Matching
Life Cycle Name Description
Predictive life cycle
A traditional approach where the majority of planning occurs up front, followed by execution of the work
Iterative life cycle
An approach that is both iterative and incremental to refine work items and deliver frequently
Incremental life cycle
An approach that provides deliverables to the customers to use immediately
Agile life cycle
An approach that allows feedback on unfinished work to improve and modify the work