New PMP Question & Answers with explanation
Match the following types of tests that are used on agile-based software projects to their description.
Matching
Testing at all levels | ||
Name of test |
Testing at all levels | Name of test | Description
|
Description |
Regression test
|
Testing the software from the start to the end to ensure the application is working correctly.
|
|
End to end test
|
A high-level test designed to identify simple failures that could jeopardize the software program.
|
|
Unit test
|
This test is performed on individual modules or individual components of source code.
|
|
Smoke test
|
This test combines software modules and tests them as a group.
|
|
Integration test
|
This test is performed after changes are made to the code or when maintenance activities are performed on the hardware the code resides on to ensure the software works the same way it did before the change.
|
Match the following agile measurements with their definitions.
Matching
Agile measurements and definitions | ||
Agile measurements | Definitions | |
Definition of done
|
A type of in-the-moment measure
|
|
Lead time
|
Typically expressed as deliverables, functionality, or features
|
|
Empirical measure
|
The time it takes to complete work on a task from the time work starts
|
|
Definition of ready
|
A checklist of elements needed to ensure the deliverable is ready for the customer to use
|
|
Response time
|
Describes the specifics of the tasks planned for the iteration before the team begins work
|
|
Cycle time
|
The time it takes for a task to go from request to completion
|
|
Capacity measures
|
The time a task waits before work starts
|
This tool and technique of the Close Project or Phase process looks at project variables and how they contributed to project outcomes. This is for the purpose of improving performance on future projects.
Select one
You are a contract project manager working with the State of Bliss. Your latest project involves rewriting the Department of Revenue's income tax system. As project manager, you have taken all the appropriate actions regarding confidentiality of data. One of the key stakeholders is a huge movie buff, and she has the power to promote you into a better position at the conclusion of this project. She's reviewing some report data that just happens to include confidential information regarding one of her favorite movie superstars. What is the most appropriate response?
Select one
You know that BAC = 2500, PV = 1250, AC = 1275, EV = 1150, and that you are experiencing typical cost variances. What is ETC?
Select one