286 New PMP People Questions & Answers with explanation

91.
During project execution, the project manager determines that communications fail to comply with the communications management plan. What should the project manager do?
Select one
92.
The project manager of a life cycle replacement project has identified stakeholders. One stakeholder is someone with whom it is difficult to work, and their behavior is causing project delays. What should the project manager do?
Select one
93.
A project manager finishes the first draft of a project management plan, and intends to present it to stakeholders for approval. However, the project management plan is long and stakeholders are geographically dispersed. The project manager has limited time to gain approval. What should the project manager do to ensure that the review of the plan is completed on time?
Select one
94.
A new project manager is developing a resource management plan but is unfamiliar with the skill sets required by the project. What should the project manager do to create the resource management plan?
Select one
95.
During a project's initiation phase, the project manager conducted a stakeholder analysis and documented all requirements. Still, some stakeholders are dissatisfied with project results because their expectations were unmet. What should the project manager have done to prevent this?
Select one
96.
Due to regulatory changes, a government agency is now a key stakeholder on a complex project. The project manager wants to develop an understanding of this new project stakeholder and any new high-level risks. What should the project manager use?
Select one
97.
A project has become so large that the single sponsor is replaced by a steering committee. What should the project manager do to accommodate this new development?
Select one
98.
A project resource completed all assigned project tasks. The resource's manager requests an immediate transfer of the resource to another project. What should the project manager do next?
Select one
99.
A project is delayed and a change is needed to obtain the desired quality level of the deliverables. The project manager issues a formal change request and communicates the change to all stakeholders. The project manager then learns that this communications approach failed to meet stakeholders' expectations. What should the project manager do?
Select one
100.
To effectively lead a project team, a project manager must help team members grow and keep them motivated throughout the project. What should a project manager do to accomplish this?
Select one