286 New PMP People Questions & Answers with explanation

61.
A kick-off meeting with stakeholders is held to discuss the draft of the project plan. During the meeting, two stakeholders disagree about the project's objective. What should the project manager have done to prevent this?
Select one
62.
Some previously unidentified stakeholders report that they have not been kept informed regarding the status of a critical project even though their functional areas are largely impacted. What should the project manager do first?
Select one
63.
During a project's development stage, a functional manager is transferred to another department and is no longer involved with the project. What should the project manager do first?
Select one
64.
A project manager presents the project charter to the steering committee. The steering committee is concerned about preassigned resource allocation because the stakeholders are unaware of their participation in the project. What should the project manager have done to avoid this?
Select one
65.
A project manager is working on a global project with resources located in different regions. What should the project manager do to address the correct channels with the right information?
Select one
66.
A project manager is working on a project for which the project sponsor is also the customer. Since the project is running smoothly, the sponsor/customer asks that the project manager send status reports only if the project is in trouble. What should the project manager do?
Select one
67.
A project manager has completed the identification of stakeholders. Previously, the project manager had difficulty managing stakeholders because no distinctions were made among them regarding influence or authority. What information needs to be included in the stakeholder register?
Select one
68.
While an activity on the critical path is being executed, the functional lead removes two project resources involved in this activity to support the resolution of a contingency situation. What should the project manager do?
Select one
69.
A new project manager joins a project during the delivery of a critical milestone. As this project has multiple stakeholders, the project manager needs to determine which stakeholders should receive information about the delivery. To what should the project manager refer?
Select one
70.
During a demo and review meeting, the progress report shows that an agile project is not on track. The project manager is surprised, because all work was purposely selected and sequenced to meet higher-level objectives. What should the project manager have done to prevent this miscommunication?
Select one