Free 2,500+ PMP questions for practice

To practice your pre-exam and review each question with detail explanation, let try with our FREE Exam tool

New matching, multiple choices exam questions from domain, process, business environment and agile which align with the new 2021 exam contain outline

142 New PMP Process Questions & Answers with explanation

51.
The project sponsor emails the project manager urgently requesting the latest measurement of cumulative work performed, expressed in terms of the approved budget. The sponsor notes that they must have this information by end of day to prepare for a critical meeting the next morning. What information is the sponsor looking for?
Select one
52.
Projects that combine elements of different life cycles to achieve a specific goal are said to use what type of project life cycle?
Select one
53.
The project team recently participated in a working session to determine the costs associated with individual activities. To produce a more accurate estimate, they broke each activity down further into smaller chunks. What will this activity yield?
Select one
54.
You’ve gathered cost estimates for the activities of your current project. Most of the activities can be completed with existing staff resources. The summary cost estimate for existing resources is $535,000. You will also need to hire contractors to perform some of the activities that require specialized skills. You’ve received a bid from a local vendor for $137,000 for these services. Which of the following statements are true?
Select two
55.
You are working on the risk management plan for your current project and need to document how the risk activities will be recorded for the benefit of future projects. Which part of the risk management plan addresses these issues?
Select one
56.
If earned value = 500, planned value = 700, and actual costs = 450, what is the cost variance?
Select one
57.
Which of the following methods should you use when you want to improve your estimates and account for risk and estimation uncertainty?
Select one
58.
Which of the following best describes individual project risk?
Select one
59.
What do functional requirements describe?
Select one
60.
A project manager learns of a recent issue that has been identified while running cable underground. The issue is deemed to be minor, so the project manager emails the project sponsor to ensure she is kept informed of all activities, as requested. What type of communication method did the project manager use?
Select one