Free 2,500+ PMP questions for practice

To practice your pre-exam and review each question with detail explanation, let try with our FREE Exam tool

New matching, multiple choices exam questions from domain, process, business environment and agile which align with the new 2021 exam contain outline

163 New PMP Process Questions & Answers with explanation

11.
Which of the following is true?
Select one
12.
Phase endings are characterized by which of the following?
Select one
13.
After meeting with several subject-matter experts, the project manager determines that the project phases will need to occur one after the other. What project life cycle is the project manager using?
Select one
14.
The project processes are iterative, are results oriented, and interact with each other. Shewhart and Deming developed a concept that reflects this idea. Which of the following is the name of this cycle?
Select one
15.
A sponsor meets with the project manager to better understand when the team will complete the project. The project manager notes that the team is completing an average of 40 story points per sprint, and as a result, they would complete the project within five iterations. She shows the sponsor a chart that reflects the projection and includes a date for each iteration. What chart is the project manager and sponsor reviewing?
Select one
16.
At the end of a sprint, the Scrum team met to talk through what went well and what could be improved. One engineer noted that the recent changes to daily stand-ups were working. Which of the following describes the actions that the Scrum team carried out?
Select two
17.
All of the following are true statements except for which one?
Select one
18.
Using the estimates provided, calculate the beta distribution: most likely estimate (ML) = 72, optimistic estimate (O) = 55, pessimistic estimate (P) = 85. Round to one decimal point.
Select one
19.
You are a project manager working on manufacturing a new product. The operational process is very detailed. One of the components of the product must measure 1 centimeter by 1 centimeter. Reliability is measured using a machine that samples one part in every hundred to assure the measurements are correct. Which of the following does this question describe?
Select one
20.
Sue leads a PMO that is in the process of shifting the organization from using predictive to more adaptive approaches to delivering project outcomes. During an Agile training session for her organization, a team member asks, “How many people are on a project team?” What response is Sue likely to provide?
Select one