175 New PMP Business environment Questions & Answers with explanation

31.
A project manager completes plans for a project and submits all documents for approval. No time is allocated for delays in approvals. What should the project manager have done to address this potential risk?
Select one
32.
The project sponsor informs the project manager that a product could have adverse health effects on customers. Because of this, the sponsor asks to change production materials. What should the project manager do?
Select one
33.
A final deliverable will not be completed on time, which is delaying project closure. What should the project manager do next?
Select one
34.
A project manager is concerned that team members spend too much time assisting operations and maintenance staff with a recently commissioned project component. To what documents should the project manager refer to validate that the component was signed off and ownership transferred?
Select one
35.
A new project manager joins an ongoing project following the resignation of the former project manager. What should the new project manager do to start guiding the team toward project success?
Select one
36.
One week prior to a kick-off meeting, a project manager meets with a key project resource to understand the complexity of the project deliverables. The resource is apprehensive about the deliverables and expresses concerns. What should the project manager do to ensure that the deliverables are realistic?
Select one
37.
A project manager is alternating between two projects with tight deadlines. They are determined to collect lessons learned from both projects, despite having limited time to do so. How should the project manager collect the lessons learned?
Select one
38.
After receiving the project charter, a project manager starts to prepare the project management plan. Since there is no historical information in the project management office (PMO), what should the project manager do next?
Select one
39.
A project manager is conducting a risk analysis based on high-level scope. If expert judgment is being used, what document is being prepared?
Select one
40.
The day before manufacturing is to start, a project manager learns that the engineering design was not accepted by the end user. What should the project manager do?
Select one